Monday, March 31, 2008
Foundation Pour
It took a week and a half, with some snow, and three people working full time to form the foundation. And today we finally poured. 60 yards of concrete, 93 1/2 total yards to bury and not be seen.
Kane again supervised the pour, and approved. No blow outs, no mistakes.
Kory played with his hose. Of course this was all pumped, can't imagine the number of wheel barrow loads this would have taken. Or how many days.
Friday, March 21, 2008
Temp Power Pole
Wednesday, March 19, 2008
Forming Foundation and Basement
Monday, March 17, 2008
Rebar Time
Friday, March 14, 2008
Thursday, March 13, 2008
Footings Pour
Wednesday, March 12, 2008
First Inspection
Need to introduce the concrete group. Kory Cline, the boss is center left. With Chris on the left, Jeremy center right, and "Bills" on the right. Kane wasn't available to be in this picture.
Today we passed the first county inspection: the Footing and Building Site Inspection. The footing step downs weren't complete, so the inspector requested that when they were done that we take pictures of them for documentation. Also, the southwest corner of the garage was 6" to close to the drain field, but got lucky and he let it pass.
Knocked off early today, Kory had another pour to do, and wanted to take advantage of the good weather.
Tuesday, March 11, 2008
Kane
To true oversight of all work done on site is being done by Kane. He is a French Mastiff that allows us to throw sticks for him, and loves to complete destroy golf balls by biting through them.
A couple of issues today. First the crawl space access from the basement was not dug out, and fixing it now would require bringing back the excavator and I'm certain Joe wouldn't appreciate digging out more of my hard pan. So now we will have a 4' cement wall to hop over to get into the crawl space. Second, my attempt at putting up the temporary power pole, failed the inspection miserably. I called in Paul's Electric to fix it for me
Monday, March 10, 2008
Cline Construction started forming up the footings. The ground was so hard under basement (in hard pan) they had to use a roto hammer to pound in some of the stakes.
Other stuff for today, I got the permit from the Dept of Labor and Industries to set up temporary power. And I got the privilege of pounding in the ground stake for the temporary pole. Its six feet long and I hit hard pan after two feet. While waiting for the temporary power, we are "borrowing" electricity from our neighbor.
Also, important to note, today the honey pot arrived. So we no longer need to wonder into the trees.
Friday, March 7, 2008
Utility Trench
A trench was dug between the house and the road along the north side of the driveway for drainage, water, power, telephone and cable tv. It took a bit of trying to get PUD to deliver the power cable, so Joe finally picked it up. We were also worried about the water connection. The meter was on the other side of the property in the southwest corner. Got lucky and found another access near the power hookup.
Garage Footings Trench
Thursday, March 6, 2008
Wednesday, March 5, 2008
Monday, March 3, 2008
Basement Digout
Subscribe to:
Posts (Atom)